Question: Given the following data, develop MRP plans for items C, D, E and F. MPS start for end items: The following table shows the MPS

Given the following data, develop MRP plans for items C, D, E and F.

MPS start for end items: The following table shows the MPS start information for two end items: item A and B. For example, we have a plan to start producing 70 units of end item A in week 2.

End Item Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
A 30 70 80
B 60 110

Bills of materials:

-End item A is made of 1 unit of item C and 1 Unit of item D.

-Item D is made of 2 units of item E and 2 units of item F.

-End item B is made of 1 unit of item C and 2 units of item F.

MRP-related information for each item:

Item Leadtime (Weeks) Lot Sizing Safety Stock Requirement Available on-hand inventory Scheduled Receipts
C 2 L4L 0 60 80 in week 1
D 1 L4L 0 80 None
E 1 FOQ (50) 0 60 None
F 1 FOQ (100) 10 30 200 in week 1

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
GR
SR
PAB
PR
POR
GR
SR
PAB
PR
POR
GR
SR
PAB
PR
POR
GR
SR
PAB
PR
POR

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!