Question: Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 3 C's
Given the following data, develop MRP tables and indicate the Planned order releases for all items.
A is an MPS item. A needs 3 C's and 2 Fs and one G. Every C needs 6 Fs and every G needs 4 Fs


Thank you!
S (15 points) Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 3 C's and 2 F's and one G. Every C needs 6 F's and every G needs 4 F's Period 1500 GR-A On hand inventory for all items is 400 and lead time for A is 1 period, LT for Fis 1 period and LT for Cand Gare 2 periods. Use lotforlot for A and a lot size of 900 or multiples of 900 for C and lot size of 2000 or multiples of 2000 for Fand G. Draw the Bill of Material Fill up the Low level code Table Low level code PO Receipt PO Release PO Receipt PO Release PO Receipt PO Release PO Receipt PO ReleaseStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts