Question: Given the following data for a horizontal well. Calculate the minimum build rates required to hit the target depth. Then drill a horizontal leg along

Given the following data for a horizontal well. Calculate the minimum build rates required
to hit the target depth. Then drill a horizontal leg along the target depth 100m. Keep in mind
that we need to be free of magnetic interference from the surface casing when we kick off so
set KOP 30 below surface casing depth.
Direction of well: 127
Find the Kick Off Point, the Build Up Rate to 90, the Measured Depth at TD and the
Displacement at EOB.
 Given the following data for a horizontal well. Calculate the minimum

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Chemical Engineering Questions!