Question: Given the following data, what sequence will you recommend using Johnsons Rule? Jobs Machine 1 ( in Days ) Machine 2 ( in Days )
Given the following data, what sequence will you recommend using Johnsons Rule?
| Jobs | Machine 1 ( in Days ) | Machine 2 ( in Days ) | Due Dates |
| A | 8 | 3 | 12 |
| B | 1 | 2 | 6 |
| C | 6 | 5 | 13 |
| D | 3 | 2 | 5 |
| E | 4 | 6 | 10 |
a.
CBDAE
b.
BACDE
c.
BECAD
d.
BEACD
e.
ABCDE