Question: Given the following data, which is an incorrect statement? Current Week = 6 BAC = $1,750 . AC = $1,480 PV = 51.430 - EV

Given the following data, which is an incorrect
Given the following data, which is an incorrect statement? Current Week = 6 BAC = $1,750 . AC = $1,480 PV = 51.430 - EV = 5950 O a Project is behind schedule O b. Project is over budget Oc Overall performance is on target Od. Overall performance is poor