Question: Given the Following EVENTS ( NODES ) and TIMES ( days ) Activity Start Finish OPTIMISTIC MOST LIKELY PESSIMISTIC A 1 2 4 1 5

Given the Following EVENTS (NODES) and TIMES (days)
Activity
Start
Finish
OPTIMISTIC
MOST LIKELY
PESSIMISTIC
A
1
2
41
50
59
B
1
3
54
60
66
C
2
4
58
70
82
D
3
4
32
41
44
What is the estimated slack time for activity D?