Question: Given the Following EVENTS ( NODES ) and TIMES ( days ) Activity Start Finish OPTIMISTIC MOST LIKELY PESSIMISTIC A 1 2 4 1 5
Given the Following EVENTS NODES and TIMES days
Activity
Start
Finish
OPTIMISTIC
MOST LIKELY
PESSIMISTIC
A
B
C
D
What is the estimated slack time for activity D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
