Question: Given the Following EVENTS ( NODES ) and TIMES ( days ) table [ [ Activity , Start,Finish,OPTIMISTIC,MOST LIKELY ] , [ A ,

Given the Following EVENTS (NODES) and TIMES (days)
\table[[Activity,Start,Finish,OPTIMISTIC,MOST LIKELY],[A,1,2,41,50],[B,1,3,54,60],[C,2,4,58,70],[D,3,4,32,41]]
What is the estimated expected (mean) time for project completion?
41 days
70 days
100 days
120 days
221 days
 Given the Following EVENTS (NODES) and TIMES (days) \table[[Activity,Start,Finish,OPTIMISTIC,MOST LIKELY],[A,1,2,41,50],[B,1,3,54,60],[C,2,4,58,70],[D,3,4,32,41]] What