Question: Given the following EVM data: Planned Value (PV): $700,000 Earned Value (EV): $650,000 Actual Cost (AC): $680,000 Questions: Calculate the Cost Variance (CV) and Schedule

Given the following EVM data:

  • Planned Value (PV): $700,000
  • Earned Value (EV): $650,000
  • Actual Cost (AC): $680,000

Questions:

  1. Calculate the Cost Variance (CV) and Schedule Variance (SV).
  2. Determine the CPI and SPI.
  3. Discuss the implications of these values for project performance and future planning.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!