Question: Planned Value ( PV ) = $ 2 3 , 0 0 0 Earned Value ( EV ) = $ 2 0 , 0 0
Planned Value PV $
Earned Value EV $
Actual Cost AC $
Budget at Completion BAC $
Cost Variance: CV EVAC
$$$
Schedule Variance: SV EVPV
$$$
Cost Performance Index: CPI EVAC
$$
Schedule Performance Index: SPI EVPV
$$ approximately
Project Progress
The cost variance of this project is negative which means that the cost overruns.
The schedule variance of this project is also negative, which indicates there are delays.
This project's cost performance index is less than which indicates that it is below what was planned.
The schedule performance index is less than which indicates that it is below planned.
Estimate at Completion using CPI: EAC BACCPI
EAC $ $
Estimate the time to finish the project using SPI: Time to finishBAVEVSPIAC
Time to finish$$$
Approximately months to completion.
Sketch the earned value chart for this project. Assume the data for month is half of the values given for PV EV and AC at the end of month
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
