Question: Planned Value ( PV ) = $ 2 3 , 0 0 0 Earned Value ( EV ) = $ 2 0 , 0 0

Planned Value (PV)= $23,000
Earned Value (EV)= $20,000
Actual Cost (AC)= $25,000
Budget at Completion (BAC)= $120,000
Cost Variance: CV= EV-AC
$20,000-$25,000=-$5,000
Schedule Variance: SV= EV-PV
$20,000-$23,000=-$3,000
Cost Performance Index: CPI= EV/AC
$20,000/$25,000=0.8
Schedule Performance Index: SPI= EV/PV
$20,000/$23,000= approximately 0.87
2. Project Progress
The cost variance of this project is negative which means that the cost overruns.
The schedule variance of this project is also negative, which indicates there are delays.
This project's cost performance index is less than 1, which indicates that it is below what was planned.
The schedule performance index is less than 1, which indicates that it is below planned.
3. Estimate at Completion using CPI: EAC= BAC/CPI
EAC= $120,000/0.8= $150,000
4. Estimate the time to finish the project using SPI: Time to finish=(BAV-EV)/(SPI*AC)
Time to finish=($120,000-$20,000)/(0.87*$25,000)
Approximately 3.86 months to completion.
Sketch the earned value chart for this project. Assume the data for month 1 is half of the values given for PV, EV, and AC at the end of month 2.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!