Question: Given the following EVM data: Planned Value (PV): $800,000 Earned Value (EV): $750,000 Actual Cost (AC): $780,000 Questions: Calculate the Cost Variance (CV) and Schedule
Given the following EVM data:
- Planned Value (PV): $800,000
- Earned Value (EV): $750,000
- Actual Cost (AC): $780,000
Questions:
- Calculate the Cost Variance (CV) and Schedule Variance (SV).
- Determine the CPI and SPI.
- Discuss the implications of these values for project performance and future planning.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
