Question: Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c.
Given the following information,
a. Draw a project network.
b. Complete the forward and backward pass, compute activity slack, and identify the critical path.
c. How sensitive is the network schedule? Briefly justify your answer?
d. Which activities have free slack?
| Activity | Predecessor | Duration (days) |
| A | None | 10 |
| B | None | 20 |
| C | A | 10 |
| D | A | 30 |
| E | B | 10 |
| F | C | 30 |
| G | C, D | 20 |
| H | D, E | 10 |
| I | F, G, H | 20 |