Question: 5. (25 points) Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the

5. (25 points) Given the following information, a. Draw a project network. b. Complete the forward and backward pass, compute activity slack, and identify the critical path. c. How sensitive is the network schedule? Briefly justify your answer? d. Which activities have free slock? Activity Predecessor Duration (days) A None 1 B None 2 C A D A, B C. E F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
