Question: Given the following information about a project: ACTIVITY PREDECESSOR DURATION A B D E- F G H I A A A B C, D
Given the following information about a project: ACTIVITY PREDECESSOR DURATION A B D E- F G H I A A A B C, D E, F D G, H 1437ONT94 4 3 7 6 2 7 9 4 Construct the Activity-On-Node network, using forward and backward passes through the network determine ES, EF, LS, LF, and slack/float for each activity, identify the critical activities and find the earliest completion time for this project. Highlight the critical path on your network.
Step by Step Solution
3.36 Rating (140 Votes )
There are 3 Steps involved in it
AON diagram and required diuration is in excel screens... View full answer