Question: Estimates Predecessors A 2 days None B 5 days A C 1 day B D 2 days A E 3 days B & D F

Estimates Predecessors

A 2 days None

B 5 days A

C 1 day B

D 2 days A

E 3 days B & D

F 12 days E & C

Draw a network diagram.

Identify the critical path, earliest start and finish and slack for each task.

Using MS Excel, produce a Gantt chart for this project.

What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?

Step by Step Solution

3.36 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

A Network diagram is as follows B Draw the table listing ES LS EF LF and Free Float and Total Float ... View full answer