Question: Given the following information about four jobs, table [ [ Job , table [ [ Processing Time ] , [ ( Days )

Given the following information about four jobs,
\table[[Job,\table[[Processing Time],[(Days)]],Due Date],[A,10,10],[B,5,8],[C,15,25],[D,8,15]]
According to EDD sequencing rule, the average flow time is:
26 days
81 days
20.25 hours
20.25 days
 Given the following information about four jobs, \table[[Job,\table[[Processing Time],[(Days)]],Due Date],[A,10,10],[B,5,8],[C,15,25],[D,8,15]] According