Question: Given the following information: Activity Predecessor Task Time (weeks) A 8 B 15 12 D A, E 10 E B, C 6 F AD 11

Given the following information: Activity
Given the following information: Activity Predecessor Task Time (weeks) A 8 B 15 12 D A, E 10 E B, C 6 F AD 11 G DF 15 H G 17 What is the latest finish time for activity D? Select one: A. 31 B. 18 OC. 21 D.8 E. 39