Question: Problem 1: Project Management (4 points) The project consists of 6 activities shown on the ADN diagram below (numbers designate activity durations in weeks). B(3)

Problem 1: Project Management (4 points) The project consists of 6 activities shown on the ADN diagram below (numbers designate activity durations in weeks). B(3) E(7) A(4) C(6) End D(7) F(5) Answer the following questions. For a each item, show your computations. 1. Apply the CPM method algorithm. For each activity, plot the bracket next to the circle showing the result of your calculations (2 points). 2. The length of the critical path is: (1 point) 3. By how many weeks can activity F be delayed without affecting the project completion time? (1 point)