Question: Given the following information and MRP table for part A; The planned - order release in week 4 will be: 1 - There will be

Given the following information and MRP table for part A; The planned-order release in week 4 will be:
1-There will be a previously arranged scheduled receipt of 400 units of part A at the beginning of week 2.
2- Manufacturing lead time is two weeks.
3- This part must be ordered in multiples of 100 units.
4-Currently, there are 700 on-hand inventory.
\table[[Parts/ Week,1,2,3,4,5,6],[\table[[Part: A,Lt=2