Question: Given the following information and MRP table for part D; The planned order receipt in week 7 will be: 1 - Currently, there are 2

Given the following information and MRP table for part D; The planned order receipt in week 7 will be:
1-Currently, there are 240 on-hand inventory.
2-There will be a previously arranged scheduled receipt of 600 units of part D at the beginning of week 6.
3- Lot-for-lot ordering is used.
4- Lead time is one week.
 Given the following information and MRP table for part D; The