Question: Given the following information, answer questions 5 - 8 . The starting Inventory is 1 5 0 and the optimum production run size is 4

Given the following information, answer questions 5-8.
The starting Inventory is 150 and the optimum production run size is 400. The demand time fence is at the end of two weeks.
On-Hand =150
1
2
3
4
5
Forecast
300
350
300
300
200
Committed Customer Orders
250
200
150
190
175
Question 5(1 point)
Saved
In which periods does MPS require planned production? (Insert your answer as sequence of period numbers separated by comma e.g.,1,2,3)
Question 5 options:
1,3,4
Question 6(1 point)
Saved
What is projected available balance (PAB) in period #3?
Question 6 options:
200
Question 7(1 point)
What is Available to Promise (ATP) in period #3?
Question 7 options:
Question 8(1 point)
Saved
What is Available to Promise (ATP) in period 4?
Question 8 options:
35

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!