Question: Given the following information, assist in developing a Master Production Schedule. Assume the Demand Fence is 1 week and the planning time fence is 2

Given the following information, assist in developing a Master Production Schedule. Assume the Demand Fence is 1 week and the planning time fence is 2 weeks, beginning inventory is 60 units and the lot size is 100 units.
Beginning Inventory=60
Week 1: forecast 100
Customer Orders=50
Week 2: forecast 100
Customer orders: 80
For week1, what is the appropriate value for the MPS?