Question: Given the following information, assist in developing a Master Production Schedule. Assume the Demand Fence is 1 week and the planning time fence is 2

Given the following information, assist in developing a Master Production Schedule. Assume the Demand Fence is 1 week and the planning time fence is 2 weeks, beginning inventory is 60 units and the lot size is 100 units.
Beginning Inventory=60
Week 1
Week 2
Forecast
100
100
Customer Orders
50
80
POH
MPS
ATP
For week1, what is the appropriate value for the MPS?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!