Question: Given the following information, develop a material requirements plan for end item A and its components (B, C, D, AND E) using the MRP Table.

Given the following information, develop a
Given the following information, develop a
Given the following information, develop a material requirements plan for end item A and its components (B, C, D, AND E) using the MRP Table. 50 and 80 units of A are needed at the beginning of weeks 6 and 8, respectively. Based on the requirement plans you developed, please answer Questions 6 through 10. Item On-Hand On-Order Lead Time Order Size A 20 I wk lot-for-lot B 2 yks 50 60 100 150 200 (Week 2) 2 wks 200 lot-for-lot Iwk 10 A B C(2) D(3) E E D(3) E 910 8 sal 50 OH