Question: Given the following information, develop a material requirements plan that will yield 400 units of product P at the start of week 7. Item Parent

Given the following information, develop a material requirements plan that will yield 400 units of product P at the start of week 7.

Item

Parent

Quantity for 1 of Parent

Currently On-Hand

Scheduled Rept (in wk)

Lead Time

Order Quantity

P1

-

-

-

-

1

Lot-for-lot

A

P

1

100

0

1

Lot-for-lot

B

P

1

0

0

1

450

C

A, B

1, 2

90

100 (wk 2)

2

600

D

B

2

50

80 (wk 2)

2

Lot-for-lot

Use the following form:

Week

1

2

3

4

5

6

7

8

Gross requirements

Schedule receipts

Projected on hand

Net requirements

Planned order receipt

Planned order release

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!