Question: Given the following information: ES for 3 - 6 is 1 5 days and ES for 4 - 6 is 3 2 days. The expected

Given the following information:
ES for 3-6 is 15 days and ES for 4-6 is 32 days.
The expected activity times are 22 days for 3-6,9 days for 4-6, and 7 days for 6-7.
(Hint: draw the network and complete a FW pass)
What is the ES for activity 6-7?
15
41
32
37
48