Question: Given the following information for a Line Balancing assignment: Use the number of following task rule first. Use the Greatest Positional Weight rule as a

Given the following information for a Line

Given the following information for a Line Balancing assignment: Use the number of following task rule first. Use the Greatest Positional Weight rule as a 'tie breaker'. If needed, use alphabetical order as a second 'tie breaker'. The company operates 8 hours per day and they produce 120 units per day. What is the correct order of tasks assigned to workstation 1? Task Immediate Time Predecessor In minutes A 0.8 B A 1.3 A,D 3.4 D 1.5 E B,C 1.8 F C, D 1.5 G E 1.0 H E, F 2.1 I G H