Question: Given the following information for a Line Balancing assignment: Use the number of following task rule first Use the Greatest Positional Weight rule as a

Given the following information for a Line
Given the following information for a Line Balancing assignment: Use the number of following task rule first Use the Greatest Positional Weight rule as a tie breaker If needed, use alphabetical order as a second se breaker The company operates 8 hours per day and they produce 120 units per day What is the correct order of tasks assigned to workstation ? Task Immediate Time Predecessor In minutes A 08 B A 13 AD 15 E BC 18 F 13