Question: Given the following information for a one year project,answer the following questions PV $22,000 EV $20,000 AC $25,000 BAC $120,000 What is the schedule performance
Given the following information for a one year project,answer the following questions PV $22,000 EV $20,000 AC $25,000 BAC $120,000 What is the schedule performance index for the project Use the CPI to calculate the estimate at completion for this project.Is the project performing better or worse than planned Use SPI to estimate how long it will take to finish this project