Question: Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC

Given the following information for a one-year

Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget c. or over budget? d. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project e. performing better or worse than planned? f. Use the SPI to estimate how long it will take to finish this project. g. Sketch the earned value chart for this project, using following figure as a guide. Estimate at completion (EAC) 120,000 100,000 Budget at completion (BAC) An EAC point above and to the right of the BAC point means the project is projected to cost more and take longer than planned 80,000 Planned value (PV) $ 60,000 40,000 Actual cost (AC) Earned value (EV) 20,000 T 1 2 3 4 5 6 7 8 9 10 11 12 13 Month Planned value (PV) --- Earned value (EV) .... Actual cost (AC)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!