Question: Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 C None 8 e b 5 C 10 C






Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 C None 8 e b 5 C 10 C 4 d,e,f 5 g 6 Which of the following is NOT a path in the network?What is the critical path?How long will it take to complete the project?What is the LS for activity c?\f\f