Question: Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 c None 8 d a 7 e b 5

Given the following information regarding a project:
Activity Predecessors Duration
a None 3
b None 6
c None 8
d a 7
e b 5
f c 10
g c 4
h d,e,f 5
i g 6
Which of the following is NOT a path in the network?
a-d-h
b-e-h
c-f-h
c-g-i
c-g-h
1 points
QUESTION 15
What is the critical path?
a-d-h
b-e-h
c-f-h
c-g-i
c-g-h
1 points
QUESTION 16
How long will it take to complete the project?
15
16
18
23
25
1 points
QUESTION 17
What is the LS for activity c?
0
3
6
7
8
1 points
QUESTION 18
What is the LF for activity h?
13
17
18
23
1 points
QUESTION 19
What is the EF for activity h?
8
12
13
18
23
1 points
QUESTION 20
What is the LF for activity i?
8
12
13
18
23

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!