Question: Given the following information, what is the project completion time? Activity Immediate Predecessor ( s ) Time ( days ) A - - 2 B

Given the following information, what is the project completion time?
Activity Immediate Predecessor(s) Time (days)
A --2
B --5
C --1
D B 10
E A, D 3
F C 6
G E, F 8
Question 4 options:
26 days
35 days
25 days
24 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!