Question: Given the following information, which is the critical path? Activity Immediate Predecessor ( s ) Time ( days ) A - - 2 B -

Given the following information, which is the critical path?
Activity Immediate Predecessor(s) Time (days)
A --2
B --5
C --1
D B 10
E A, D 3
F C 6
G E, F 8
Question 18 options:
B-D-E-G
B-D-F-G
C-F-G
A-E-G

Step by Step Solution

There are 3 Steps involved in it