Question: Saved Given the following information, which is the critical path? Activity Immediate Predecessor ( s ) Time ( days ) A - - 2 B
Saved
Given the following information, which is the critical path?
Activity Immediate Predecessors Time days
A
B
C
D B
E A D
F C
G E F
Question options:
BDFG
BDEG
AEG
CFG