Question: Given the following network diagram, supposes tasks A and D may be reduced to one day, at a cost of $ 1 5 per day

Given the following network diagram, supposes tasks A and D may be reduced to one
day, at a cost of $15 per day of reduction. Also, tasks E, G, and H may be reduced in
duration by one day at a cost of $25 per day of reduction. What is the leastcost approach
to crash the project by two days? What is the shortest crashed duration, the new
critical path, and the leastcost approach to the shortest crash duration?