Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ES EF S LF SLACK

Given the following partially completed Project
Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ES EF S LF SLACK A 2 - 0 20 20 LB 10 A 2122 12o I 8 A 2 106 | 14 | 4 D 7 B 12 19 12 19 0 5 B, C 12 17 E I 5 DET IGI 4 17 | 21 FINISH ES