Question: Given the following problem. Include the data of 40 days Day Arrivals Station 1 Station 2 Station 3 Completed 1 2 0.37 0.09 0.07 1
Given the following problem. Include the data of 40 days
| Day | Arrivals | Station 1 | Station 2 | Station 3 | Completed |
| 1 | 2 | 0.37 | 0.09 | 0.07 | 1 |
| 2 | 2 | 0.24 | 0.13 | 0.13 | 2 |
| 3 | 1 | 0.31 | 0.25 | 0.13 | 1 |
| 4 | 0 | 0 | 0.03 | 0 | 1 |
| 5 | 2 | 0.37 | 0.17 | 0.07 | 1 |
| 6 | 1 | 0.18 | 0.21 | 0.13 | 2 |
| 7 | 0 | 0 | 0 | 0 | 0 |
| 8 | 1 | 0.04 | 0 | 0 | 0 |
| 9 | 3 | 0.58 | 0.38 | 0.2 | 3 |
| 10 | 3 | 0.66 | 0.33 | 0.24 | 3 |
| 11 | 1 | 0.09 | 0.04 | 0.02 | 1 |
| 12 | 2 | 0.46 | 0.19 | 0.13 | 2 |
| 13 | 3 | 0.47 | 0.53 | 0.2 | 3 |
| 14 | 2 | 0.45 | 0.22 | 0.2 | 2 |
| 15 | 2 | 0.33 | 0.17 | 0.07 | 2 |
| 16 | 5 | 0.62 | 0.31 | 0.22 | 3 |
| 17 | 2 | 0.71 | 0.56 | 0.31 | 4 |
| 18 | 2 | 0.34 | 0.11 | 0.07 | 2 |
| 19 | 1 | 0.21 | 0.17 | 0.11 | 1 |
| 20 | 2 | 0.37 | 0.26 | 0.16 | 3 |
| 21 | 3 | 0.55 | 0.45 | 0.2 | 1 |
| 22 | 3 | 0.45 | 0.5 | 0.11 | 3 |
| 23 | 3 | 0.66 | 0.6 | 0.22 | 3 |
| 24 | 4 | 0.73 | 0.58 | 0.29 | 5 |
| 25 | 7 | 0.74 | 0.55 | 0.11 | 1 |
| 26 | 1 | 0.72 | 0.94 | 0.47 | 7 |
| 27 | 2 | 0.37 | 0.2 | 0.13 | 3 |
| 28 | 3 | 0.22 | 0.01 | 0.07 | 1 |
| 29 | 2 | 0.69 | 0.45 | 0.24 | 3 |
| 30 | 5 | 0.42 | 0.41 | 0.08 | 1 |
| 31 | 2 | 0.86 | 0.51 | 0.4 | 6 |
| 32 | 3 | 0.55 | 0.58 | 0.21 | 3 |
| 33 | 1 | 0.18 | 0.12 | 0.07 | 2 |
| 34 | 5 | 0.64 | 0.24 | 0.18 | 2 |
| 35 | 2 | 0.64 | 0.48 | 0.29 | 5 |
| 36 | 0 | 0 | 0 | 0 | 0 |
| 37 | 7 | 0.71 | 0.33 | 0.2 | 2 |
| 38 | 3 | 1 | 0.48 | 0.38 | 6 |
| 39 | 5 | 0.58 | 0.36 | 0.15 | 2 |
| 40 | 3 | 1 | 0.51 | 0.4 | 6 |
1. Compute Coecient of Variation (C.V.) for orders arrived.
The potential answers are:
A: 0.71.
B: 0.75.
C: 0.67.
D: 0.65.
E: 0.66.
2. Compute the average inventory.
The potential answers are:
A: 0 units.
B: 1.4 units.
C: 1.54 units.
D: 1.7 units.
E: 1.5 units.
3 . Compute the average flow time. Suppose throughput is equal to orders completed.
The potential answers are:
A: 0 days.
B: 0.59 days.
C: 0.57 days.
D: 0.61 days.
E: 0.76 days.
4. Compute average utilization of Station 1. The potential answers are:
A: 0.55.
B: 0.51.
C: 0.36.
D: 0.46.
E: 0.48.
5. Compute the daily capacity of station 1. Suppose throughput is equal to orders completed.
The potential answers are:
A: 8.26 units.
B: 0 units.
C: 6.4 units.
D: 5.35 units.
E: 5.06 units.