Question: Given the following product tree, explode, offset, and determine the gross and net requirements. All lead time are 1 week , and the quantities required
Given the following product tree, explode, offset, and determine the gross and net requirements. All lead time are 1 week, and the quantities required are shown in parentheses. The lot size for all parts is (lot-for-lot). The master production schedule calls for the completion of 100 As in week 4, and 50 in week 5. There are 300 Bs scheduled to be received in week 1, and 200 Ds in week 3. There are also 20 As available.
What is the Gross Requirement for product D in week 3 ?

Given the following product tree, explode, offset, and determine the gross and net requirements. All lead time are 1 week, and the quantities required are shown in parentheses. The lot size for all parts is (lot-for- lot). The master production schedule calls for the completion of 100 As in week 4, and 50 in week 5. There are 300 Bs scheduled to be received in week 1, and 200 ds in week 3. There are also 20 AS available. B (2) C(1) D (1) E (1) D (2) B (1) What is the Gross Requirement for product D in week 3 ? 4 3 2 1 Week Part Low-Level Code Gross Requirements A Scheduled Receipts Projected Available 20 Lead Time: 1 Week Net Requirements Planned Order Receipt Planned Order Release Gross Requirements B Scheduled Receipts Projected Available Lead Time: Net Requirements 1 Week Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Lead Time: Net Requirements 1 Week Planned Order Receipt Planned Order Release Gross Requirements D Scheduled Receipts Projected Available Lead Time: Net Requirements 1 Week Planned Order Receipt Planned Order Release Gross Requirements E Scheduled Receipts Projected Available Lead Time: Net Requirements 1 Week Planned Order Receipt Planned Order Release 5 4 3 2 Part Low-Level Code A Lead Time: 1 Week B Lead Time: 1 Week Week Gross Requirements Scheduled Receipts Projected Available 20 Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Lead Time: 1 Week D Lead Time: 1 Week E Lead Time: 1 Week