Question: Given the following project: Act. Preceding Crash Cost Maximum Crash Normal Time Activity (in million $) Time (in months) (in months) A - 0 0
Given the following project:
Act. Preceding Crash Cost Maximum Crash Normal Time Activity (in million $) Time (in months) (in months)
A - 0 0 1
B A 10 2 3
C A 5 1 4
D B 6 1 3
E C 7 2 4
F D, E 9 1 3
SLACK TIME = Late Starting Time Early Starting Time OR Late Finish Time Early Finish Time
To reduce the project time as much as possible given its characteristics, what activity or activities can be crashed?