Question: Given the following Project Activity Description and Network Diagram, select the Critical Path. Activity Duration Predecessor ES EF A 5 0 B 17 5
Given the following Project Activity Description and Network Diagram, select the Critical Path. Activity Duration Predecessor ES EF A 5 0 B 17 5 C 14 5 D 10 22 11 32 12 32 1 44 EFG G O START A, 5 O 5 5 5. L 5 00 R 8 A A A, B, C B, D C, D E, F, G B, 17 C, 14 22 22 19 22 22 22 D, 10 32 32 32 33 32 32 LS LF SLACK 5 0 5 0 22 5 22 0 19 8 22 3 32 22 32 0 43 33 44 1 44 32 44 0 45 44 45 0 E, 11 F, 12 43 44 44 44 44 44 G, 1 45 45 FINISH A-B-D-F-G A-B-D-E-G A-B-E-G A-D-E A-C-F-G A-C-D-E-G O A-C-D-F-G
Step by Step Solution
There are 3 Steps involved in it
In project management the critical path is the sequence of project activities that adds up to the longest overall duration This determines the shortes... View full answer