Question: Given the following Project Activity Description and Network Diagram, select the Critical Path. Activity Duration Predecessor ES | 0 20 A 8 24 TA 8

Given the following Project Activity Description

Given the following Project Activity Description and Network Diagram, select the Critical Path. Activity Duration Predecessor ES | 0 20 A 8 24 TA 8 A,B,C 32 B, D 50 C, D 50 E, F, G 75 EFLSLF SLACK 8 0 8 28 12 32 328 32 O 50 32 50 10 69 56 75 6 75 50 75 0 77 75 770 19 25 8 28 5069 B, 20 E, 19 1232 5675 08 3250 77 START A, 8 D, 18 G, 2 FINISH 3250 7577 50 C, 24 F, 25 32 5075 A. A-B-D-E-G B. A-B-D-F-G C. A-C-D-E-G D. A-D-E E. A-C-D-F-G F. A-C-F-G G. A-B-E-G