Question: Given the following project, answer the below questions: Activity Predecessor 1 1 2 3 4 5 6 7 8 8 Duration estimates (days) a, m,

Given the following project, answer the below
Given the following project, answer the below questions: Activity Predecessor 1 1 2 3 4 5 6 7 8 8 Duration estimates (days) a, m, b 1,4,5 2, 3, 4 6, 10, 13 6,6,7 2,2, 2 1,2,3 5,8,9 12, 16, 19 2 3 4,5 2 a) Draw the project network. b) Perform a PERT analysis of the following project. c) Find the probability of completing the project between 17 and 19 days inclusive