Question: Given the following project information: 1) Manually compute the early/late, start/finish, and slack times of each activity 2) Determine the planned project duration 3) Identify

Given the following project information:

1) Manually compute the early/late, start/finish, and slack times of each activity

2) Determine the planned project duration

3) Identify the critical path

Given the following project information: 1)

Lights 1 H G J Lag 1 Pave Paint Parkin lines Open Lot A Post Signs 1 B Prepare Site 3 2 1 1 3 Lag 10 E F D Dig Trenches 1 Lay Back FH 5 Pipe 5 3 Signage 1 Lag 3 Lag 3 Legend ES ID EF SL Description SL LS Duration LF 1