Question: Given the following project information: 1) Manually compute the early/late, start/finish, and slack times of each activity 2) Determine the planned project duration 3) Identify

Given the following project information: 1) Manually compute the early/late, start/finish, and slack times of each activity 2) Determine the planned project duration 3) Identify the critical path

DONT FORGET THE LAGGiven the following project information: 1)

Lights 1 G H J A B Lag 1 Pave Paint Parkin lines Open Lot 0 Post Signs Prepare Sito 2 1 1 1 3 Lag 10 D E F 1 Dig Trenches Lay Pipe Back Fill Signage 5 5 3 1 Legend Lag 3 Lag 3 ES ID EF SL Description SL LS Duration LF