Question: Given the following project information Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time A - 2 4 6 B - 3 4 10
Given the following project information
| Activity | Immediate Predecessor | Optimistic time | Most likely time | Pessimistic time |
| A | - | 2 | 4 | 6 |
| B | - | 3 | 4 | 10 |
| C | B | 11 | 7 | 5 |
| D | A | 14 | 18 | 22 |
| E | A | 3 | 5 | 9 |
| F | C, E | 2 | 3 | 4 |
| G | D | 4 | 3 | 5 |
| H | F, G | 6 | 6 | 6 |
I) Draw or explain the activities relationship with the immediate predecessors.
II) Calculate the expected time for each activity.
III) Calculate the variance in each activity.