Question: Given the following project information Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time A - 2 4 6 B - 3 4 10

Given the following project information

Activity

Immediate Predecessor

Optimistic time

Most likely time

Pessimistic time

A

-

2

4

6

B

-

3

4

10

C

B

11

7

5

D

A

14

18

22

E

A

3

5

9

F

C, E

2

3

4

G

D

4

3

5

H

F, G

6

6

6

I) Draw or explain the activities relationship with the immediate predecessors.

II) Calculate the expected time for each activity.