Question: Given the following project network: a . Identify the critical path. A - C - D - F A - C - E - F

Given the following project network:
a. Identify the critical path.
A-C-D-F
A-C-E-F
A-B-D-F
b. Identify the early start for task D.
c. Identify the late finish for task C.
d. Calculate slack for task E.
 Given the following project network: a. Identify the critical path. A-C-D-F