Question: Given the following project network: a-1. Identify the critical path. A-C-D-F A-B-D-F A-C-E-F a-2. In this table, identify the earliest start and finish for each
Given the following project network:
a-1. Identify the critical path.
-
A-C-D-F
-
A-B-D-F
-
A-C-E-F
a-2. In this table, identify the earliest start and finish for each task. Note that the column header of "earliest completion" is the same as early finish. (Leave no cells blank - be certain to enter "0" wherever required.) 
b. In this table, identify the late start, late finish, and slack for each task. Note that the task order is now in backward-pass order. Also note the table header of "Latest completion" is the same as late finish. As a reminder, Slack = LF - EF, or can also be calculated as LS - ES. (Leave no cells blank - be certain to enter "0" wherever required.)