Question: Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period

Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.
\table[[,,,,,,Time Period],[Task,DUR,ES,LF,SL,Budget (PV),1,2,3,4,5,6,7,8,9,10,11,12,13,14,15],[A,2,0,2,0,400,200,200,,,,,,,,,,,,,],[B,6,2,8,0,2400,,,200,600,200,600,200,600,,,,,,,],[C,5,2,9,2,1500,,,200,400,500,100,300,,,,,,,,],[D,4,8,12,0,1620,,,,,,,,,420,400,400,400,,,],[E,3,7,12,2,900,,,,,,,,300,400,200,,,,,],[F,3,12,15,0,590,,,,,,,,,,,,,200,90,300],[Period PV total,200,200,400,1,000,700,700,500,900,820,600,400,400,200,90,300],[Cumulative PV total,200,400,800,1,800,2,500,3,200,3,700,4,600,5,420,6,020,6,420,6,820,7,020,7,110,7,410]]
(Do not round intermediate calculations. Round your table answer entries to the nearest whole number.)
\table[[End of Period 4,,EV,AC,PV,CV,SV],[Actual % Complete],[A,Finished,,500,,,],[B,50,,900,,,],[C,35,,500,,,]]
 Given the following project network and baseline information below, complete the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!