Question: Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4

Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period8?
Given the project network and baseline information below, comple

End of Period 4 Task Actual % Complete EV AC PV CV SV 300 400 1000 800 50% 33% 0% 0% 500 600_ Cumulative Totals End of Period 8 Task Actual % Complete EV AC PV CV SV 300 2200 -1500 300 400 2400 1500- tnishet - 25% 33% 0% -300- Cumulative Totals

Step by Step Solution

3.45 Rating (174 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The project appears to be doing nicely In both periods 4 and 8 the cost variance is positi... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

177-B-M-L-P-M (1465).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!