Question: Given the following project network, baseline, and status information, develop status reports for periods 2 , 4 , 6 , 8 , and complete the
Given the following project network, baseline, and status information, develop status reports for periods and complete the performance indexes table. Calculate the forecasted estimate at completion EAC and the forecasted variance at completion VAC Based on your data, what is your assessment of the current status of the project? Is it at completion?
Use the project network, baseline chart, and status report table below to complete this learning activity:
Paths
The Paths are:
ACF
ADF
BDF
BEF
Activity A points to both Activity B and Activity D
Activity B points to both Activity D and Activity E
Activity C Activity D and Activity E all point to Activity F
For Activity A:
ES
EF
SL
SL
LA
LF
DUR
For Activity B:
ES
EF
SL
SL
LA
LF
DUR
For Activity C:
ES
EF
SL
SL
LA
LF
DUR
For Activity D:
ES
EF
SL
SL
LA
LF
DUR
For Activity E:
ES
EF
SL
SL
LA
LF
DUR
For Activity F:
ES
EF
SL
SL
LA
LF
DUR
Budget Allocations
ID
Budget $
A
B
C
D
E
F
Total
Cumulative
Status Reports
Status Report: Ending Period
$
Task
Complete
EV
AC
PV
CV
SV
A
B
Cumulative Totals
Status Report: Ending Period
$
Task
Complete
EV
AC
PV
CV
SV
A
B
Cumulative Totals
Status Report: Ending Period
$
Task
Complete
EV
AC
PV
CV
SV
A
B
C
D
E
Cumulative Totals
Status Report: Ending Period
$
Task
Complete
EV
AC
PV
CV
SV
A
B